Course curriculum

    1. Outage Economics - The True Value of a Well Planned and Executed Maintenance Outage

    2. The Nature of Projects

    1. The Evolution of Critical Path Techniques

    1. Introduction to The Precedence Network and Network Logic

    2. Exercise 1 - Simple Network Exercise "Getting up in the Morning"

    3. Exercise 1 - Simple Network Exercise Solution "Getting up in the Morning"

    1. Building Critical Path Networks

    2. Notes on Activities and Sequencing

    3. Case Study 1 - Changing the wheel on an Automobile

    4. Case Study 1 - Solution - Precedence Network - Changing the wheel on an Automobile.

    5. A Practice Example - Precedence Networks - Building a Swimming Pool

    6. A Practice Example - Building a Critical Path Network (Worked Solution)

    1. Introduction to the “World of Time” with Precedence Networks

    2. Exercise 2a Time Analyzing the Network (The Forward Pass)

    3. Solution to Exercise 2a Time Analyzing the Network (The Forward Pass)

    4. Introduction to the “World of Time” with Precedence Networks - Part 2 The Reverse Pass and The Concept of Float

    5. Exercise 2b - Time Analyzing the Network - (The Reverse Pass and the Calculation of Float)

    6. Solution to Exercise 2b - Time Analyzing the Network (The Reverse Pass and the calculation of Float)

About this course

  • $4,425.00
  • 42 lessons
  • 7 hours of video content